2.5 MWh Peak-Shaving Storage, Jiaxing Textile Plant

2.5 MWh Peak-Shaving Storage, Jiaxing Textile Plant

In Mar 2024, a 2.5 MWh storage system began operation at a textile mill in Jiaxing. It comprises 35 LY-HS8K-3P inverters and 5 MWh of batteries, operating a two-cycle peak-shaving strategy.

The first-year peak-load offset is 38 % with a simple payback of 2.9 years. The system was commissioned within four months and is now operating without faults, prompting the client to initiate a second phase.